A suggested approach to site storage resources in transmission planning models

Published online by Cambridge University Press:  10 September 2020

Rao Konidena*
Affiliation:
Rakon Energy LLC, Roseville, MN, USA
*
Address all correspondence to Rao Konidena at [email protected]
Get access

Abstract

Placing a large storage project at one transmission node influences the transmission flows in the model. Hence, planners need an approach that estimates future storage services and logically places storage at multiple transmission nodes.

In planning models, it is hard to forecast which service storage might provide at any given hour because storage provides a wide variety of services such as capacity benefit, peaker replacement, reduction in renewable energy curtailment, and ancillary services. But transmission planning models are required to address North American Electric Reliability Corporation (NERC) reliability standards and criteria, with assumptions for planned additions of generation, transmission, and demand response resources. Hence, planners must assume a basic set of services for storage resources.

And this paper outlines a suggested approach to site storage resources in planning models by focusing on the generator interconnection queue for utility-scale storage and energy-intensive industries for commercial and industrial customers.

Type
Perspective
Copyright
Copyright © The Author, 2020, published on behalf of Materials Research Society by Cambridge University Press

Access options

Get access to the full version of this content by using one of the access options below. (Log in options will check for institutional or personal access. Content may require purchase if you do not have access.)

References

New York Independent System Operator (NYISO): Distributed energy resources webpage. Available at: https://www.nyiso.com/distributed-energy-resources-der- (accessed July 30, 2020).Google Scholar
BAL-502-RFC-02: Planning resource adequacy reliability criteria can be found here. Available at: https://www.nerc.com/files/BAL-502-RFC-02.pdf (accessed July 30, 2020).Google Scholar
Transmission Planning (TPL): Transmission planning reliability standards start with the designation “TPL” here. Available at: https://www.nerc.net/standardsreports/standardssummary.aspx (accessed July 30, 2020).Google Scholar
The capability of generators to respond to system needs in 4 secs. Automatic Generation Control (AGC). Response to NERC BAL 001 standard.Google Scholar
PJM: PJM notes in a 2015 document, “PJM's current regulation requirement is 700 Effective MWs on-peak and 525 Effective MWs off-peak” source. Available at: http://www.pjm.com/~/media/committees-groups/committees/oc/20150701-rpi/20150701-fast-response-regulation-resources-operational-impact-problem-statement.ashx (accessed July 30, 2020).Google Scholar
PJM: Source: PJM Manual 12 Balancing Operations. Available at: https://www.pjm.com/~/media/documents/manuals/m12.ashx (accessed July 30, 2020).Google Scholar
FERC Order 819: “Frequency response is a resource standing by to provide autonomous, pre-programmed changes in output to rapidly arrest large changes in frequency until dispatched resources can take over while regulation service is centrally dispatched through automatic generation control (AGC) and is not focused exclusively on frequency control.” FERC Order 819. Available at: https://www.ferc.gov/industries-data/electric/general-information/electric-market-based-rates/important-orders/order-no-819 (accessed July 30, 2020).Google Scholar
Energy Storage Association: U.S. Energy Storage Monitor website. Available at: https://energystorage.org/resources/industry-resources/us-energy-storage-monitor/ (accessed July 30, 2020).Google Scholar
For the purposes of this exercise, Alliant Energy – Interstate Power has been left out. Alliant Energy has sold distribution assets in MN however still owns transmission.Google Scholar
Utility Dive article: “The utility wants to add a 2 MW, 6 MWh battery and a 1 MW solar array to reduce the load on the feeder and transformer at the location by shifting the load curve so there is “a smaller overload for a shorter length of time”. Available at: https://www.utilitydive.com/news/as-xcel-pushes-non-wire-alternatives-solarstorage-pilot-sparks-utility-ow/414650/ (accessed July 30, 2020).Google Scholar
Connexus Energy: GRE member Connexus Energy storage projects link. Available at: https://www.connexusenergy.com/save-money-and-energy/programs-rebates/solar-energy/solar-storage (accessed July 30, 2020).Google Scholar
Otter Tail Power Company: OTP Service Area Map. Available at: https://www.otpco.com/about-us/communities-we-serve/ (accessed July 30, 2020).Google Scholar
Energy Storage Association (ESA): Energy Storage Association (ESA) web link for storage as peakers. Available at: https://energystorage.org/flexible-peaking-resource/ (accessed July 30, 2020).Google Scholar
Dirty Energy Big Money: In New York City, a Clean Energy Group as part of the PEAK Coalition “Dirty Energy Big Money” report found capacity payments for peakers to the order of $4 billion. Available at: https://www.cleanegroup.org/wp-content/uploads/Dirty-Energy-Big-Money.pdf (accessed July 30, 2020).Google Scholar
National Renewable Energy Laboratory (NREL): The Potential for Battery Energy Storage to Provide Peaking Capacity in the United States. Available at: https://www.nrel.gov/docs/fy19osti/74184.pdf (accessed July 30, 2020).Google Scholar
Clean Energy Group: Clean Energy Group link for peaker locations. Available at: https://www.cleanegroup.org/ceg-projects/phase-out-peakers/peaker-plant-map/ (accessed July 30, 2020).Google Scholar
ERCOT: See ERCOT Methodologies for Determining Minimum Ancillary Service Requirements document. Available at: http://www.ercot.com/content/wcm/key_documents_lists/161483/8_2020_ERCOT_Methodologies_for_Determining_Minimum_Ancillary_Service_Requirements.pdf (accessed July 30, 2020).Google Scholar
ERCOT: ERCOT paper, “System Inertial Frequency Response Estimation and Impact of Renewable Resources in ERCOT Interconnection”. Available at: http://www.ercot.com/content/gridinfo/etts/keydocs/System_Inertial_Frequency_Response_Estimation_and_Impact_of_.pdf (accessed July 30, 2020).Google Scholar
Hornsdale Power Reserve: The Hornsdale battery response was in milliseconds during the loss of a 560 MW generating unit. Source: slide 9, Hornsdale Power Reserve. Available at: https://arena.gov.au/assets/2019/02/hornsdale-power-reserve.pdf (accessed July 30, 2020)Google Scholar
Amazon Web Services sustainability (AWS): Link to Amazon Web Services sustainability projects in solar and wind. Available at: https://aws.amazon.com/about-aws/sustainability/ (accessed July 30, 2020).Google Scholar
greentechmedia (gtm): Wal-Mart announcement “Wal-Mart, Advanced Microgrid Solutions to Turn Big-Box Stores Into Hybrid Electric Buildings” in California. Available at: https://www.greentechmedia.com/articles/read/wal-mart-to-turn-big-box-stores-into-hybrid-electric-buildings (accessed July 30, 2020).Google Scholar
U.S. Energy Information Administration (EIA) International Energy Outlook 2016: Chapter 7, Industrial sector energy consumption. Available at: https://www.eia.gov/outlooks/ieo/pdf/industrial.pdf (accessed July 30, 2020).Google Scholar
Understanding Demand Charges for General Secondary Rates: Each utility may charge peak demand charge differently, however in general this is the best definition for peak demand charge: “demand charges are based on the highest level of electricity supplied at one time during the billing period and at the time of day it's needed by your business”. Available at: https://www.we-energies.com/business/elec/understand_demand_charges.pdf (accessed July 30, 2020).Google Scholar
Large Energy Users Database: Large energy users are defined as manufacturing facilities with total site energy consumption greater than 0.2 TBtu per year. Available at: https://www.energy.gov/eere/amo/downloads/large-industrial-facilities-state (accessed July 30, 2020).Google Scholar