No CrossRef data available.
Article contents
Emergency repair of the hearth wall of BF A at Aceralia
Published online by Cambridge University Press: 27 April 2006
Abstract
Aceralia blast furnace A suffered a 28-days emergency repair inSeptember 2004, due to accelerated wear of the hearth walls andsevere damage of the cast iron staves at the bosh area. Consideringthe shortage of supplies, Aceralia resorted to non conventionalrepair methods in order to prolong the campaign by one year, untilfull relining: small format carbon bricks and carbon ramming massfor the hearth and tapholes and steel staves at the bosh.
- Type
- Research Article
- Information
- Metallurgical Research & Technology , Volume 103 , Issue 4: Haut-fourneauFour électriqueCoulée continueUltra steelsBâtiment , April 2006 , pp. 160 - 167
- Copyright
- © La Revue de Métallurgie, 2006