No CrossRef data available.
Article contents
New continuous annealing line for Rasselstein
Published online by Cambridge University Press: 17 January 2008
Abstract
In December 2003, Rasselstein GmbH Germany placed an orderwith the consortium VAI (Consortium leader) and Drever (Furnace)for the erection of the new continuous annealing line n° 5. The constructionof this annealing line takes place in a new building simultaneouslywith the construction of the tinning line n° 12. This modernline is unique in that for the first time it is planned to homogeneouslyanneal strips in widths from 800 to 1,400 mm. The future capacityamounts to 360,000 t. After annealing and finishing rolling thematerial is coated in a tinning line after which it finds use as an intermediateproduct for the beverage and packing industries.
- Type
- Research Article
- Information
- Metallurgical Research & Technology , Volume 104 , Issue 12: SteelmakingCold rollingUse of steel , December 2007 , pp. 598 - 603
- Copyright
- © La Revue de Métallurgie, 2007